Stan Iverson Library: Rancho Seco Timeline The Disturbing History of Rancho Seco
1966-1969
SMUD purchases 2,100 acres in southeast Sacramento County for a nuclearpower plant. Construction begins on the cooling towers.
1971
- SMUD raises rates...even though Rancho Seco hasn't produced a singlekilowatt-hour of electricity.
- The day Rancho Seco is dedicated there is a forced shutdown of the reactor(unknown to those attending the dedication ceremony)... a portent of things tocome. [10/19/74]
- The turbine breaks down. The plant is shut down for 13 of the first 18months of operation.
1976
- Loose parts are found in Rancho Seco's generator. SMUD says the find "willnot cause any additional lost time." The plant is down for six months.[4/9/76, SB ]
1978
- Rancho Seco shuts down four times. Problems are due to a dangerouslyfast cooldown.
1979
- Radioactive iodine is found in milk from cows grazing near Rancho Seco. [Quarterly Radiation Report on Rancho Seco ]
1980
- Rancho Seco shuts down six times. Problems occurred with pipe supports, reactor coolant leaks, malfunctions, turbine bearings and feedwaterflow. [9/26/83, SU ]
- SMUD is fined $25,000 by the NRC for violating federal safety standards.
1981
- A state report on emergency planning estimates that a serious nuclearaccident at Rancho Seco could result in as many as 76,000 deaths and 110,000injuries. [11/2/80, SB ]
- Rancho Seco shuts down 12 times. Problems are due to steam generator tubeleaks, feedwater, reactor coolant pump and turbine vibrations. [9/26/83, SU ]
1982
- Rancho Seco shuts down 11 times, due to problems with the turbine,steam leaks, oil pressure and reactor trips. [9/26/83, SU ]
- SMUD is fined $120,000 for violating federal safety regulations.
- The steam generator leaks again...more radioactive steam escapes. Anothershut-down.
1983
- Rancho Seco shuts down five times, due to maintenance, re-fueling,modifications, oil pressure in turbine generator, heat imbalance in reactor andleak in steam generator tube. [9/26/83, SU ]
- The steam generator tubes leak again and more radioactive steam escapesinto the atmosphere. The plant is shut down again.
- SMUD faces a lack of skilled workers for Rancho Seco. [3/6/83, SB]
1984
- Rancho Seco is on the NRC's list of the ten worst nuclear plants inthe U.S. in overall assessment of management performance. [3/28/89, PublicCitizens Mishaps Report, NRC ]
- More than two billion gallons of water containing radiation levels abovefederal guidelines have been dumped from Rancho Seco into a creek that feedsthe Cosumnes and Mokelumne Rivers, SMUD officials confirmed. [4/14/84, SB ]
- Two workers are killed by high-pressure steam bursting from a boiler atRancho Seco.
- An explosion and fire shut down Rancho Seco for 38 days.
1985
- SMUD raises rates twice...by nearly 30 percent. SMUD has the firstbudget deficit in its history. From January 1, 1985 to March 31, 1988, RanchoSeco operates only three months (out of three and one-quarter years).
- On December 26, Rancho Seco suffers the third-fastestshut-down in U.S. reactor history when a control circuit malfunctions. The sudden temperature change could have cracked the reactor vessel and led to ameltdown.
- SMUD customers are now paying 40 percent more than a year ago. Rancho Secowork is $27 million over budget and another rate increase is being considered.
1986
- Sacramentans for SAFE Energy (SAFE) calls for the SMUD board of directors to commission an independent, comprehensive study of the safety andeconomic risks associated with Rancho Seco as well as a comparison ofalternative means of meeting our energy needs.
- Rancho Seco assistant manager for nuclear operations Dan Whitney saidplant managers sometimes deliberately withheld information about systemshortcomings when questioned by the NRC. [5/22/86, SB ]
- SMUD admits that Rancho Seco was "mismanaged, mismaintained and misoperated" its entire lifetime. [5/20/86, SB ]
- Two Rancho Seco workers are fired for drug abuse. They claim there is drugabuse throughout the plant.
1987
- wo water leaks lead to the release of approximately 10,000 gallons ofradioactive water, some of it flowing into the nearby creek, outside of theplant's boundaries...[3/28/89, Public Citation of Mishaps, NRC ]
- In 1987, SMUD pays more than $350,000 in cash bonuses to fill positions atRancho Seco. [7/10/88, SB ]
- "Rates have increased 84 percent since March 1985, leading to ratepayer dismay and a situation in which half of SMUD households pay more thanif served by surrounding Pacific Gas and Electric Company. " [10/23/87, SB]
- Chief of nuclear operations, John Ward, is fired despite reputation as afixer of hopeless cases."It was like being in charge of the Keystone Kops,"says Ward. [9/23/86]
1988
- "Closing Rancho Seco is the option for the future of SMUD that makes the most sense." [3/2/88, Sacramento Bee Editorial Staff ]
- "The never-ending series of mishaps are beginning to look like a veryhigh-budget Marx Brothers film, with Harpo in charge of warning the city shouldthere be an emergency." [2/19/88, TV 40 Editorial Comment ]
- A SMUD-commissioned, $824,000 QUEST study team recommends closure ofRancho Seco, saying that unstable operation of Rancho Seco could bankrupt SMUD.
- Rancho Seco operates at less than 37%--even less than its lifetimecapacity average of 39%. Rates have increased almost 92% since March 1985 dueto Rancho Seco problems. [INPO ]
- The October 1988 SMUD bond prospectus states, "The District has concluded that terminating Rancho Seco in June 1989 would not have a materiallyadverse impact on the District's operations through December, 1999." [SMUD]
- Measure B (to close Rancho Seco) loses on the June ballot by the narrowestof margins--only two votes per precinct. Measure C (to give Rancho Seco a trialrun) barely passes.
- Rancho Seco supporters promise stability and low electric rates for SMUD.However, immediately following the June 1988 election, SMUD General ManagerRichard Byrne is fired, Rancho Seco chief of nuclear operations resigns andSMUD discloses the need for additional rate increases. Two SMUD chiefs get$520,000 in severance pay and bonuses.
- Former SMUD general manager Richard Byrne said he was "stifled, pressured and threatened by pro-Rancho Seco board members who wanted to keeppotentially damaging information from reaching the public before the June 7,1988 election. [6/18/88, SB ]
- SMUD gives out $248,500 in bonuses to middle- and upper-level employees inMay for ''extraordinary service.'' About 80 percent ($197,000 was awarded toRancho Seco managers and the balance to employees at SMUD headquarters.[9/1/88,SB]
- SMUD secretly paid out more than 970,000 in cash and benefits to eight managerswho were forced to leave the utility during the past two years. [11/17/88, SB ]
- Operating Rancho Seco in 1988 cost nearly twice the amount it would havecost SMUD to have purchased the same amount of electricity from otherutilities. [12/26/88, SU ]
- December 12--Operators try to restart Rancho Seco with malfunctioningvalves. They rig the system in a manner for which there are no writtenprocedures. One of two steam generators runs dry. NRC officials say operatorstook the plant through "uncharted waters" and showed poor judgment inhandling the restart.
1989
- On January 31 Rancho Seco shuts down. Two days later, radioactive gasis released into the environment. The plant is down for 45 days. Bill Chapin,Rancho Seco plant mechanical maintenance supervisor and co-chairman of theRancho Seco Political Action Committee says, "I think there's no doubt,the Ranch cannot have another breakdown between now and June, politicallyspeaking." A day after his quote, Rancho Seco goes down yet another time. [3/28/89, SB ]
- SMUD and PG&E contract ensures cheap, reliable power for Sacramentothrough l999. [2/27/89, SU ]
- The nuclear industry's own Institute of Nuclear Power Operations preparesa report on the recent shutdowns at Rancho Seco, saying that Rancho Seco'sprior operating history as well as recent shutdowns "cause us to have arenewed concern over the quality of Rancho Seco operations." [INPO]
- SMUD pays $1,230 for one Rancho Seco employee's clothing as part of the "distinctiveattire'' program. Jackets, pants, shirts and ties have already cost $72,000;laundry bills, $2,500 a month--all ultimately paid by the ratepayers.
- The plant comes to an abrupt halt (is scrammed) on the 10th anniversary ofthe Three Mile Island meltdown. High-level radioactive gasses are vented to theatmosphere. On April 8 the reactor is started, even though the cause of theMarch 28 accident has not been found and malfunctioning equipment (from theMarch 15 accident) has not been repaired. [3/29/89, SB, SU ]
- June 6th, 1989 Sacramento Citizens go to the polls and vote to permanentlyclose Rancho Seco.
Sources: SB: Sacramento Bee, SU Sacramento Union xxx The above was a postercreated for Measure K on June 6, 1989
Use your back button to return to your previous page
Or visit
@nti-CopyRite 2000-3000, more or less
The Stan Iverson Memorial Library
Corrections, additions, suggestions to
BleedMeister David BrownVisit the complete Stan Iverson Memorial Library
The Stan Iverson Memorial Library is freely produced for your use or abuse by Recollection Used Books